基于4D-BIM的施工资源动态管理与成本实时监控Resource Dynamic Management and Cost Real-time Monitoring in Building Construction Based on 4D-BIM
张建平;范喆;王阳利;黄志刚;
Zhang Jianping1,Fan Zhe1,Wang Yangli2,Huang Zhigang2(1.Department of Civil Engineering,Tsinghua University,Beijing 100084,China;2.Shanghai Zhuyuan Construction Management Co.,Ltd.,Shanghai 200122,China)
摘要(Abstract):
针对建筑工程施工资源和成本管理的复杂性以及工程建造成本超过预算现象,通过建立4D施工资源信息模型和系统开发,实现了施工阶段对人力、材料和机械等资源的动态管理和工程成本的实时监控,为提高施工项目管理水平和成本控制能力探索了新途径和方法。
Because of the complexity of construction resource and cost management,construction costs are often over budget.To solve this problem,authors built a 4D construction resource information model and developed a system with the functionalities of dynamic resource management to manage the human resources,raw materials and construction machines dynamically and to real-time monitor the engineering cost.This research suggests a new approach to improve the level of construction management and cost control.
关键词(KeyWords):
BIM;4D资源动态管理;成本实时监控;建筑施工
BIM;4D resource dynamic management;cost real-time monitoring;building construction
基金项目(Foundation): 国家“十一五”科技支撑计划项目(2006BAJ01B07-03)
作者(Authors):
张建平;范喆;王阳利;黄志刚;
Zhang Jianping1,Fan Zhe1,Wang Yangli2,Huang Zhigang2(1.Department of Civil Engineering,Tsinghua University,Beijing 100084,China;2.Shanghai Zhuyuan Construction Management Co.,Ltd.,Shanghai 200122,China)
参考文献(References):
- [1]Eastman C,Teicholz P,Sacks R,et al.BIM handbook:a guideto building information modeling for owners,managers,designers,engineers and contractors[M].New York.John Wiley&SonsInc.2008.
- [2]Wang H J,Zhang J P,Chau K W,et al.4D dynamicmanagement for construction planning and resource utilization[J].Automation in Construction,2004,13(5):575-589.
- [3]祝元志.数字技术再掀建筑产业革命?——BIM在建筑行业的应用、前景与挑战[J].建筑,2010(3):8,14-26.
- [4]张建平,曹铭,张洋.基于IFC标准和工程信息模型的建筑施工4D管理系统[J].工程力学,2005,22(S1):221-227.
- [5]GB50500—2008建设工程工程量清单计价规范[S].北京:中国计划出版社,2008.
- [6]杨娟,张星.建设项目信息集成模型与支撑技术标准[J].施工技术,2009,38(10):109-112.
- [7]胡振中.基于BIM和4D技术的建筑施工冲突与安全分析管理[D].北京:清华大学,2009.
- BIM
- 4D资源动态管理
- 成本实时监控
- 建筑施工
BIM - 4D resource dynamic management
- cost real-time monitoring
- building construction
- 张建平
- 范喆
- 王阳利
- 黄志刚
Zhang Jianping1- Fan Zhe1
- Wang Yangli2
- Huang Zhigang2(1.Department of Civil Engineering
- Tsinghua University
- Beijing 100084
- China
- 2.Shanghai Zhuyuan Construction Management Co.
- Ltd.
- Shanghai 200122
- China)
- 张建平
- 范喆
- 王阳利
- 黄志刚
Zhang Jianping1- Fan Zhe1
- Wang Yangli2
- Huang Zhigang2(1.Department of Civil Engineering
- Tsinghua University
- Beijing 100084
- China
- 2.Shanghai Zhuyuan Construction Management Co.
- Ltd.
- Shanghai 200122
- China)